Upper Weyand Pipeline Project
The project must be complete by March 1st, 2024. The project is located adjacent and through rural driveways and orchards approximately 1/2 mile north of Midway Road from 1/2 mile east of Batavia Road to Porter Road, near Dixon in Solano county California. The project generally includes installing approximately 1,660 feet of 48-inch diameter, DR l7 HDPE pipe and steel fittings; connections to existing pipes and installation of valve risers and access structures; demolition and removal of reinforced concrete vents and junction boxes; removal and abandonment of existing pipelines; installation of valves, and appurtenances, and surface restoration. The District has pre-purchased 48" HDPE pipe and fittings and will be furnishing an assortment of fabricated steel pipe special fittings, see Appendix g for complete list.
Addendum 1
(click to expand/collapse)
Name | Size | |||
Upper Weyand Pipeline - Addendum No 1 | 240.6 KB |