Chadbourne Lateral Pipeline Project
The Project must be complete by March 1, 2023 and will require simultaneous work on two headings. The project is along the east side of Abernathy Road, beginning just north of Mankas Coner Rd and terminating just south of Piazza Lane in Fairfield, CA
Status
Bidding Closed
Bid Date | 8/11/22 10:00am |
Company & Contacts
Solano Irrigation District
Nancy McWilliams
nmcwilliams@sidwater.org
Location
Fairfield, CA
The Engineer’s Estimate is $1,470,000.00